Learn all about our progress

Transparency is what we are most proud of at Sastal, so we want you to join us throughout the development process.

2024
August
2024
Hydraulic base in second stage

Forming and laying of material for hydraulic base with bench material for second stage

August
2024
Hydraulic base in first stage

Forming and laying of material for hydraulic base with bench material for first stage

July
2024
Ironworks for structures

Enabling and cutting of ironwork for construction of metal structure of facade and access.

June
2024
Gardening of the access to Sastal
May
2024
Home water pumping station
May
2024
Pouring sidewalks and pedestrian crossings
April
2024
Electrical power connection
March
2024
Green Areas for Access to Sastal
February
2024
Painting of offices, warehouses and bathrooms
January
2024
Sidewalk curbs

We are starting 2024 with a bang, beginning with the curbs on the sidewalks. On January 8, 2024, we will resume work with this new step.

2023
December
2023
Pipe placement and electric current recording

We begin with the work of laying the pipe and the electric current records.

October
2023
Installation of water and drinking water and electricity pipes

We started with the trenching work for the installation of the clean water and electricity pipes.

August
2023
Laying cables on power poles

In August 2023, we began laying cables on power poles.

July
2023
Drilling and installation of electric power poles

We started with the drilling and placement of poles for electric power.

2022
November
2022
Dirt roads of the first streets of the first and second stages

The dirt roads of the first streets of the first and second stages of Sastal are formed.