Learn all about our progress

Transparency is what we pride ourselves most on at Sastal, which is why we’re sharing our progress timeline with you.

Check out daily updates on Instagram or Facebook.

2025
September
2025
Supplier Entry
2025
August
2025
Light in entrance gate
2025
July
2025
Garden on Sidewalks
2025
June
2025
Staff entry
2025
May
2025
+500 meters of Perimeter Fence
2025
April
2025
Installation of security cameras
2025
March
2025
Central curb

Filling of central benches

February
2025
Sidewalk

Construction work begins on the central median curbs

January
2025
Access to services enabled
2024
December
2024
Water Network

Cleaning and piping for third and fourth stage drinking water network

December
2024
Laying of electrical pipeline
December
2024
Ditch Cut

Start of work on trench cutting for third and fourth stage drinking water and electricity pipelines.

November
2024
Water house

Leveling and cementing of water shed with cementing material

November
2024
Security cameras
November
2024
Placement of Access Bars
October
2024
Dirt road in phase 3 and 4

Earthworks on streets begin in third stage

September
2024
Hydraulic base in second stage

Forming and laying of material for hydraulic base with bench material for second stage

August
2024
Hydraulic base in first stage

Forming and laying of material for hydraulic base with bench material for first stage

July
2024
Ironworks for structures

Enabling and cutting of ironwork for construction of metal structure of facade and access.

June
2024
Gardening of the access to Sastal
May
2024
Home water pumping station
May
2024
Pouring sidewalks and pedestrian crossings
April
2024
Electrical power connection
March
2024
Green Areas for Access to Sastal
February
2024
Painting of offices, warehouses and bathrooms
January
2024
Sidewalk curbs

We are starting 2024 with a bang, beginning with the curbs on the sidewalks. On January 8, 2024, we will resume work with this new step.

2023
December
2023
Pipe placement and electric current recording

We begin with the work of laying the pipe and the electric current records.

October
2023
Installation of water and drinking water and electricity pipes

We started with the trenching work for the installation of the clean water and electricity pipes.

August
2023
Laying cables on power poles

In August 2023, we began laying cables on power poles.

July
2023
Drilling and installation of electric power poles

We started with the drilling and placement of poles for electric power.

2022
November
2022
Dirt roads of the first streets of the first and second stages

The dirt roads of the first streets of the first and second stages of Sastal are formed.